Plans Surface For Memorial Park Redevelopment Project

Construction of the expanded park is expected to proceed in stages based on funding and approvals

The City of Santa Monica has proposed plans to expand and renovate Memorial Park, a project that will increase the park’s footprint from 10.3 acres to 13.2 acres by incorporating the adjacent Fisher Lumber site. The redevelopment aims to modernize public recreation facilities, improve accessibility, and enhance community gathering spaces.

According to a notice issued by the city, the project will be completed in four phases. The first phase will begin with the demolition of portions of the park and the Fisher Lumber site, followed by the construction of a synthetic turf field, a covered parking area, rooftop tennis and pickleball courts, and streetscape improvements along Colorado Avenue and 14th Street. A temporary dog park or playground may also be included.

In the second phase, further demolition along Colorado Avenue and most of 16th Street will clear space for another synthetic turf field, a new community hub building, and a universally accessible playground. A temporary natural grass field will also be created.

The third phase will focus on expanding and renovating the existing skate park, adding a walking loop with exercise stations, and replacing youth baseball and softball fields along Olympic Boulevard. Streetscape improvements will also be implemented along 16th Street and Olympic Boulevard.

The final phase will see the redevelopment of the community recreation center at the southwest corner of the park, along with additional improvements along 14th Street.

A draft Environmental Impact Report (EIR) is being prepared to assess the project’s potential effects on air quality, hazardous materials, and cultural resources, among other environmental considerations. Public input is being solicited on the scope of the report, with a public scoping meeting scheduled for March 12 at Memorial Park Craft Room.

Construction of the expanded park is expected to proceed in stages based on funding and approvals. While the total cost remains uncertain, a 2019 estimate placed the price at over $116 million, a figure that is likely to have increased due to rising construction and material costs, according to Urbanize LA.

The public can review project plans and submit comments through April 1 via the City of Santa Monica’s environmental review website.

in Hard, News
Related Posts

Santa Monica Councilmember Clarifies Position on Fairview Library Amid Public Outcry

April 10, 2025

April 10, 2025

The statement came during a packed City Council meeting April 8, where dozens of residents—many holding signs reading “Save the...

Hal Frederick, Beloved Venice Restaurateur Who Helped Name Abbot Kinney Blvd., Dies at 91

April 10, 2025

April 10, 2025

In 1987, he opened Hal’s Bar & Grill on what was then still called West Washington Boulevard—a street Frederick helped rename Hal...

Fundraising Efforts Continue for Palisades Restaurants on the Road to Recovery

April 9, 2025

April 9, 2025

Months after the Pacific Palisades fire, local restaurants Reel Inn, Vittorios, and Rocco’s continue to rally community support as fundraising...

Palisades Recovery Coalition to Present Rebuilding Draft Plan

April 9, 2025

April 9, 2025

Described as a “structured, methodical approach” to post-disaster recovery, the plan aims to streamline materials management, workforce deployment, and legislative...

Man Attempts to Steal Route 66 Sign, No Arrest Made

April 9, 2025

April 9, 2025

Police said the man left the area without further incident A man was detained Sunday afternoon after police found him...

Marina del Rey Marks 60 Years with Harbor Tours, Nostalgic Parties, and Deals Around Town

April 9, 2025

April 9, 2025

Around town, restaurants and businesses are marking the milestone with promotions tied to the year of the marina’s dedication Marina...

Art Museum Opens Photo Exhibit Honoring First Responders of LA Wildfires

April 9, 2025

April 9, 2025

The exhibition includes photographs of firefighters, paramedics, law enforcement officers, and volunteers working during the height of the crisis A...

Caruso to Address Palisades Residents in Upcoming Webinar on Rebuilding Efforts

April 9, 2025

April 9, 2025

Caruso has remained vocal in recent months about the slow pace of recovery in the region and has criticized city...

New Santa Monica Place Management Aims to Restore Mall as “Heart and Soul” of Community

April 8, 2025

April 8, 2025

The firm plans to attract new retailers and restaurants in anticipation of the 2028 Olympics Commercial real estate firm Prism...

(Video) Makeshift Memorial Created at Dog Park for Venice Shooting Victim

April 7, 2025

April 7, 2025

Zachary Melton, Known by Locals as “Turtle”, Was Protecting a Woman in an Altercation with the Suspected Gunman Zachary Melton,...

800 Lots Cleared as Debris Removal Progress Continues in Palisades

April 7, 2025

April 7, 2025

Residents can track ongoing cleanup efforts via an interactive progress map The U.S. Army Corps of Engineers has completed debris...

Asbestos Being Stored at Temescal Gateway Park by USACE

April 7, 2025

April 7, 2025

The park, a well-trafficked entrance to the Topanga State Park system, has been closed to the public since the cleanup...

Venice Man With Alzheimer’s Reported Missing; Police Seek Public’s Help

April 7, 2025

April 7, 2025

Richard Hunter, 79, Disappeared After Leaving His Home Saturday Morning Authorities and family members are seeking the public’s help in...

Marina del Rey Beachfront Building Blends Residential, Commercial Space for $12M

April 7, 2025

April 7, 2025

The listing highlights a 270-degree view spanning the Pacific Ocean, Venice Pier, and the Los Angeles skyline A four-story mixed-use...

Community Rally Planned to Save Santa Monica’s Fairview Library

April 7, 2025

April 7, 2025

Supporters Urge Santa Monica City Council to Keep the Library Open By Judith Meister, Chair, Santa Monica Library Board A...